Hunter Valley Capacity Improvement Program

Project
Hunter Valley Capacity Improvement Program
Client
Australian Rail Track Corporation (ARTC)
Location
Sector
Services
Status
Completed

Project Synopsis:

The Hunter Valley Capacity Improvement Program was essential to enable the sufficient rail network capacity to meet future industry demand.

Services Rendered:

(Executives of Projence delivered the following services)

Development of the HV Provisioning Facility, including

  • Constraints assessment
  • Concept Design
  • Budget Pricing
  • Review of Environmental Factors

With regards to ARTC’s previous Project Management Standard PP-157 (now EGP-20-01), our personnel have completed end of phase reports which were endorsed by the Rail Capacity Group (RCG) and ARTC Budget Investment Committee (BIC) and approved by the ARTC Board for the following projects:

    • Minimbah Bank 3rd Track – Phase 3, Phase 4 and Phase 5
    • Maitland to Minimbah 3rd Track – Phase 1, Phase 2 and Phase 3
    • Hunter Valley Provisioning Facility – Phase 1
    • Bi-Directional Signalling – Phase 6